Generation Interconnection Procedures
Generation Interconnection Procedures
Generator Interconnection Procedures
The following procedures, agreements and forms are required to initiate the various interconnection studies and processes required through NSP's Generator Interconnection Procedures. All completed forms should be sent to: Nova Scotia Power Inc. Interconnection Engineer can be reached at: Interconnect@nspower.ca |
Notices
Please be advised of the following notices: 1. 2. 3. To be eligible for inclusion in the Interconnection System Impact Study stage, and thereby advance the Interconnection Request’s initial Queue Position, the Interconnection Customer must meet the progression milestone requirements of Section 7.2 of the GIP at least ten (10) Business Days prior to the Interconnection System Impact Study commencement date. For clarity, item 7.2 (i) – provision of a detailed stability model for the generator(s) shall mean:
NSPI-TPR-015-2: PSSE and PSCAD Model Requirements and NSPI-TPR-014-1: Model Quality Testing will undergo revision as the grid evolves and performance criteria changes. The most up to date version will be provided as they become available. 4. Notice Date: September 18, 2024 Study Group 39 was added to the GIP Study Calendar in response to the anticipated timing of the provincial Green Choice Program procurement. Schedules for Study Groups 38 and 40 (previously numbered 39, May 2025) were not affected. Projects entering SIS Group 39 which are not electrically remote from projects in SIS Group 38 will require the associated Group 38 studies to be progressed sufficiently before they can commence. 5. Notice Date: May 7, 2025 The Study Group 40 Progression Milestone due date, Study Period Commencement date, and Study Period End date have been updated to align with the province’s revised milestone schedule for Green Choice Program projects. The updated dates below apply to all projects seeking entry into Study Group 40.
6. Notice Date: May 21, 2025 As requested by the Province, Nova Scotia Power has further extended the Milestone Due Date, Commencement Date, and End Date for GIP Study Group 40. This extension is made to align with the Province’s revised milestone schedule for Green Choice Program Projects. The updated dates below apply to all projects seeking entry into Study Group 40.
7. Notice Date: June 6, 2025 As requested by the Province, Nova Scotia Power has further extended the Milestone Due Date, Commencement Date, and End Date for GIP Study Group 40. This extension is made to align with the Province’s revised milestone schedule for Green Choice Program Projects. The updated dates below apply to all projects seeking entry into Study Group 40.
*End of Notice* |
Transmission Interconnection Procedures (Applicable to transmission systems 69,000 volts and higher)
|
Generation Interconnection Procedure (GIP) Study Calendar
Interconnection Request Queue
Distribution Generator Interconnection Procedures (Applicable to distribution systems 26,400 volts and lower)
|
Distribution Generation Interconnection Procedure (DGIP) Study Calendar
Technical Requirements for Transmission and Distribution Interconnected Generators
PSS®E and PSCADTM Model Requirements
The information on this page has been updated on November 27, 2025
If there are any issues with OASIS please contact NSPSOAdmin@nspower.ca


