Transmission Customer Procedures

Transmission Customer Procedures


 
Application for Eligible Customer Status

The Application for Eligible Customer Status is required to initiate the various kinds of transmission services offered under NSPI's OATT.

The completed form should be mailed to:

Nova Scotia Power Inc.
5 Long Lake Drive
Halifax, NS
Canada
B3S 1N8

Attention: Natasha Flynn, Senior Compliance Engineer

Once the application has been completed, the original, signed document must be sent by mail.

 

Eligible Customers

Eligible customers will be sent the application specific to the service they requested. Following approval of that application, customers will be asked to sign one of the following Service Agreements (provided here for reference.)
 

 

Transmission System Interconnection Requirements

 

Active Transmission Service Studies

 

Transmission Service SIS Scope

 

Bulk Power

 

The information on this page was last updated on December 10, 2024 

If there are any issues with OASIS please contact NSPSOAdmin@nspower.ca